|
538 WorkRate |
Name : _________________ |
||
|
If Ann does a job in 5 days, and Bob does it in 8 days, how long do they take together? (Nearest to the 10th...) |
If Ann does a job in 9 days, and Bob does it in 9 days, how long do they take together? (Nearest to the 10th...) |
|
+( ) |
|
( )+ |
|
++[[ ]]++ |
||
| 538 3.1 1.6 2.2 2 3.9 ( 12.8 ) 4.5 2.7 2 2.2 3.9 ( 15.3 ) [[ 28.1 ]] | ||
|
|
||