|
789 WorkRate |
Name : _________________ |
||
|
If Ann does a job in 8 days, and Bob does it in 6 days, how long do they take together? (Nearest to the 10th...) |
If Ann does a job in 2 days, and Bob does it in 7 days, how long do they take together? (Nearest to the 10th...) |
|
+( ) |
|
( )+ |
|
++[[ ]]++ |
||
| 789 3.4 3.9 1.5 2.9 2.9 ( 14.6 ) 1.6 1.6 1 2.5 3.9 ( 10.6 ) [[ 25.2 ]] | ||
|
|
||