234 WorkRate |
Name : _________________ |
||
|
If Ann does a job in 2 days, and Bob does it in 6 days, how long do they take together? (Nearest to the 10th...) |
If Ann does a job in 10 days, and Bob does it in 7 days, how long do they take together? (Nearest to the 10th...) |
|
+( ) |
|
( )+ |
|
++[[ ]]++ |
||
| 234 1.5 2.4 3.3 3.7 2.9 ( 13.8 ) 4.1 2 3.4 2.2 1.5 ( 13.2 ) [[ 27 ]] | ||
|
|
||