|
468 WorkRate |
Name : _________________ |
||
|
If Ann does a job in 4 days, and Bob does it in 10 days, how long do they take together? (Nearest to the 10th...) |
If Ann does a job in 8 days, and Bob does it in 2 days, how long do they take together? (Nearest to the 10th...) |
|
+( ) |
|
( )+ |
|
++[[ ]]++ |
||
| 468 2.9 2 1.9 3.7 2.3 ( 12.8 ) 1.6 3.4 2.1 2.2 1.7 ( 11 ) [[ 23.8 ]] | ||
|
|
||