|
120 WorkRate |
Name : _________________ |
||
|
If Ann does a job in 10 days, and Bob does it in 2 days, how long do they take together? (Nearest to the 10th...) |
If Ann does a job in 7 days, and Bob does it in 7 days, how long do they take together? (Nearest to the 10th...) |
|
+( ) |
|
( )+ |
|
++[[ ]]++ |
||
| 120 1.7 1.5 2.2 2.9 3.3 ( 11.6 ) 3.5 3.6 1.7 4.2 2.9 ( 15.9 ) [[ 27.5 ]] | ||
|
|
||