|
793 WorkRate |
Name : _________________ |
||
|
If Ann does a job in 8 days, and Bob does it in 5 days, how long do they take together? (Nearest to the 10th...) |
If Ann does a job in 2 days, and Bob does it in 6 days, how long do they take together? (Nearest to the 10th...) |
|
+( ) |
|
( )+ |
|
++[[ ]]++ |
||
| 793 3.1 3.6 3.8 2.9 2.9 ( 16.3 ) 1.5 1.7 3.8 2.4 2.7 ( 12.1 ) [[ 28.4 ]] | ||
|
|
||