|
502 WorkRate |
Name : _________________ |
||
|
If Ann does a job in 5 days, and Bob does it in 8 days, how long do they take together? (Nearest to the 10th...) |
If Ann does a job in 4 days, and Bob does it in 9 days, how long do they take together? (Nearest to the 10th...) |
|
+( ) |
|
( )+ |
|
++[[ ]]++ |
||
| 502 3.1 1.7 1.7 2 4.2 ( 12.7 ) 2.8 1.7 2.7 2.1 1.6 ( 10.9 ) [[ 23.6 ]] | ||
|
|
||