|
118 WorkRate |
Name : _________________ |
||
|
If Ann does a job in 10 days, and Bob does it in 2 days, how long do they take together? (Nearest to the 10th...) |
If Ann does a job in 5 days, and Bob does it in 8 days, how long do they take together? (Nearest to the 10th...) |
|
+( ) |
|
( )+ |
|
++[[ ]]++ |
||
| 118 1.7 3.7 1.6 3.1 3.6 ( 13.7 ) 3.1 1.3 3.9 2.2 1.2 ( 11.7 ) [[ 25.4 ]] | ||
|
|
||