|
915 WorkRate |
Name : _________________ |
||
|
If Ann does a job in 9 days, and Bob does it in 5 days, how long do they take together? (Nearest to the 10th...) |
If Ann does a job in 8 days, and Bob does it in 5 days, how long do they take together? (Nearest to the 10th...) |
|
+( ) |
|
( )+ |
|
++[[ ]]++ |
||
| 915 3.2 2.7 2.3 3.6 1.6 ( 13.4 ) 3.1 2.9 2.7 1.6 1.3 ( 11.6 ) [[ 25 ]] | ||
|
|
||