If Ann does a job in 4 days, and Bob does it in 6 days, how long do they take together? (Nearest to the 10th...) |
If Ann does a job in 4 days, and Bob does it in 6 days, how long do they take together? (Nearest to the 10th...) |
|
+( ) |
|
( )+ |
|
++[[ ]]++ |
||
| 466 2.4 3.2 4.1 1.3 2.2 ( 13.2 ) 2.4 4.4 1.2 2.7 3.8 ( 14.5 ) [[ 27.7 ]] | ||
|
|
||