|
493 WorkRate |
Name : _________________ |
||
|
If Ann does a job in 5 days, and Bob does it in 8 days, how long do they take together? (Nearest to the 10th...) |
If Ann does a job in 6 days, and Bob does it in 4 days, how long do they take together? (Nearest to the 10th...) |
|
+( ) |
|
( )+ |
|
++[[ ]]++ |
||
| 493 3.1 2.2 4.1 3.3 2 ( 14.7 ) 2.4 1.7 3.4 3.4 3.6 ( 14.5 ) [[ 29.2 ]] | ||
|
|
||