864  WorkRate1
2

Name : _________________

 

refresh

40 people can do a job in 5 days. How many days would it take if there were only 8 people?



24 people can do a job in 10 days. How many days would it take if there were only 4 people?



8 people can do a job in 5 days. How many days would it take if there were only 2 people?



20 people can do a job in 8 days. How many days would it take if there were only 5 people?



14 people can do a job in 5 days. How many days would it take if there were only 7 people?



24 people can do a job in 11 days. How many days would it take if there were only 8 people?



45 people can do a job in 12 days. How many days would it take if there were only 9 people?



49 명의 일꾼들이 어떤일을 끝내는데 7 일이 걸린다. 만일 7 명의 일꾼들이 하면 며칠 걸려 끝내겠는가?



40 people can do a job in 11 days. How many days would it take if there were only 8 people?



42 people can do a job in 10 days. How many days would it take if there were only 7 people?



+(         )

 

(         )+

++[[          ]]++

864    25 60 20 32 10 ( 147 )   33 60 49 55 60 ( 257 )   [[ 404 ]]