|
937 WorkRate |
Name : _________________ |
||
|
If Ann does a job in 9 days, and Bob does it in 7 days, how long do they take together? (Nearest to the 10th...) |
If Ann does a job in 4 days, and Bob does it in 7 days, how long do they take together? (Nearest to the 10th...) |
|
+( ) |
|
( )+ |
|
++[[ ]]++ |
||
| 937 3.9 4.4 1.6 2.5 2.4 ( 14.8 ) 2.5 1.6 1.6 2.7 3.2 ( 11.6 ) [[ 26.4 ]] | ||
|
|
||