|
971 WorkRate |
Name : _________________ |
||
|
If Ann does a job in 9 days, and Bob does it in 6 days, how long do they take together? (Nearest to the 10th...) |
If Ann does a job in 9 days, and Bob does it in 6 days, how long do they take together? (Nearest to the 10th...) |
|
+( ) |
|
( )+ |
|
++[[ ]]++ |
||
| 971 3.6 1.7 3.3 3.2 2.5 ( 14.3 ) 3.6 3 4.7 1.6 1.6 ( 14.5 ) [[ 28.8 ]] | ||
|
|
||