|
947 WorkRate |
Name : _________________ |
||
|
If Ann does a job in 9 days, and Bob does it in 9 days, how long do they take together? (Nearest to the 10th...) |
If Ann does a job in 8 days, and Bob does it in 10 days, how long do they take together? (Nearest to the 10th...) |
|
+( ) |
|
( )+ |
|
++[[ ]]++ |
||
| 947 4.5 3.8 2.5 1.4 1.3 ( 13.5 ) 4.4 2.7 3.1 1.5 3.6 ( 15.3 ) [[ 28.8 ]] | ||
|
|
||