If Ann does a job in 8 days, and Bob does it in 10 days, how long do they take together? (Nearest to the 10th...) |
If Ann does a job in 2 days, and Bob does it in 4 days, how long do they take together? (Nearest to the 10th...) |
|
+( ) |
|
( )+ |
|
++[[ ]]++ |
||