|
522 WorkRate |
Name : _________________ |
||
|
If Ann does a job in 5 days, and Bob does it in 7 days, how long do they take together? (Nearest to the 10th...) |
If Ann does a job in 2 days, and Bob does it in 4 days, how long do they take together? (Nearest to the 10th...) |
|
+( ) |
|
( )+ |
|
++[[ ]]++ |
||
| 522 2.9 3.6 2.9 2.9 2.5 ( 14.8 ) 1.3 1.7 3.4 3.1 2.2 ( 11.7 ) [[ 26.5 ]] | ||
|
|
||