|
758 WorkRate |
Name : _________________ |
||
|
If Ann does a job in 7 days, and Bob does it in 3 days, how long do they take together? (Nearest to the 10th...) |
If Ann does a job in 2 days, and Bob does it in 5 days, how long do they take together? (Nearest to the 10th...) |
|
+( ) |
|
( )+ |
|
++[[ ]]++ |
||
| 758 2.1 3.1 3.1 1.6 2 ( 11.9 ) 1.4 4.4 3.3 1.9 2 ( 13 ) [[ 24.9 ]] | ||
|
|
||