28 people can do a job in 10 days. How many days would it take if there were only 7 people?



36 people can do a job in 9 days. How many days would it take if there were only 6 people?



27 people can do a job in 9 days. How many days would it take if there were only 9 people?



16 people can do a job in 10 days. How many days would it take if there were only 4 people?



14 people can do a job in 6 days. How many days would it take if there were only 2 people?



6 people can do a job in 10 days. How many days would it take if there were only 3 people?



20 people can do a job in 12 days. How many days would it take if there were only 4 people?



42 명의 일꾼들이 어떤일을 끝내는데 10 일이 걸린다. 만일 6 명의 일꾼들이 하면 며칠 걸려 끝내겠는가?



35 people can do a job in 5 days. How many days would it take if there were only 7 people?



10 people can do a job in 9 days. How many days would it take if there were only 2 people?



+(         )

 

(         )+

++[[          ]]++