|
355 WorkRate |
Name : _________________ |
||
|
If Ann does a job in 3 days, and Bob does it in 2 days, how long do they take together? (Nearest to the 10th...) |
If Ann does a job in 7 days, and Bob does it in 4 days, how long do they take together? (Nearest to the 10th...) |
|
+( ) |
|
( )+ |
|
++[[ ]]++ |
||
| 355 1.2 2 4.4 2.2 1.2 ( 11 ) 2.5 3.6 1.7 2.3 3.4 ( 13.5 ) [[ 24.5 ]] | ||
|
|
||