|
136 WorkRate |
Name : _________________ |
||
|
If Ann does a job in 10 days, and Bob does it in 8 days, how long do they take together? (Nearest to the 10th...) |
If Ann does a job in 5 days, and Bob does it in 9 days, how long do they take together? (Nearest to the 10th...) |
|
+( ) |
|
( )+ |
|
++[[ ]]++ |
||
| 136 4.4 1.7 2.2 3.4 3.9 ( 15.6 ) 3.2 2 2.2 3.6 2.2 ( 13.2 ) [[ 28.8 ]] | ||
|
|
||