899 WorkRate |
Name : _________________ |
||
|
If Ann does a job in 9 days, and Bob does it in 4 days, how long do they take together? (Nearest to the 10th...) |
If Ann does a job in 3 days, and Bob does it in 5 days, how long do they take together? (Nearest to the 10th...) |
|
+( ) |
|
( )+ |
|
++[[ ]]++ |
||
| 899 2.8 3.3 3.7 1 2.2 ( 13 ) 1.9 2.2 4.2 1.6 2.4 ( 12.3 ) [[ 25.3 ]] | ||
|
|
||