If Ann does a job in 5 days, and Bob does it in 8 days, how long do they take together? (Nearest to the 10th...) |
If Ann does a job in 9 days, and Bob does it in 9 days, how long do they take together? (Nearest to the 10th...) |
|
+( ) |
|
( )+ |
|
++[[ ]]++ |
||
| 520 3.1 3.6 1.7 3.2 2.7 ( 14.3 ) 4.5 2.7 2 2.4 1.6 ( 13.2 ) [[ 27.5 ]] | ||
|
|
||