|
540 WorkRate |
Name : _________________ |
||
|
If Ann does a job in 5 days, and Bob does it in 6 days, how long do they take together? (Nearest to the 10th...) |
If Ann does a job in 4 days, and Bob does it in 7 days, how long do they take together? (Nearest to the 10th...) |
|
+( ) |
|
( )+ |
|
++[[ ]]++ |
||
| 540 2.7 1.5 2.2 2.5 2.8 ( 11.7 ) 2.5 2.9 2.9 2 1.5 ( 11.8 ) [[ 23.5 ]] | ||
|
|
||