|
272 WorkRate |
Name : _________________ |
||
|
If Ann does a job in 2 days, and Bob does it in 8 days, how long do they take together? (Nearest to the 10th...) |
If Ann does a job in 6 days, and Bob does it in 9 days, how long do they take together? (Nearest to the 10th...) |
|
+( ) |
|
( )+ |
|
++[[ ]]++ |
||
| 272 1.6 2.9 2.3 3.6 3.4 ( 13.8 ) 3.6 2.9 2.9 3.8 4.2 ( 17.4 ) [[ 31.2 ]] | ||
|
|
||